Skip To Main Content

Fixed Header

Landing Nav

26-B12-24 Roof Replacement at Hyde Middle School

  • Scope of Work:  Removal of existing asphalt shingles at Hyde Middle School: Buildings 100, 200, 300, 600, 700, 900, and 1200 down to the wood deck. New underlayment and asphalt shingles installed in accordance with manufacturer specifications.
  • Mandatory Bid Walk: A mandatory prebid conference and site visit will be held on March 13, 2026 at 1:00 p.m. at Hyde Middle School 19325 Bollinger Rd, Cupertino, CA 95014
  • Contractor License required: C-39
  • Engineer's Estimate: $510,400.00
  • Bid Opening Date and Time: March 27 @ 2:00 p.m.
  • Construction: 6/10/26 - 7/31/26
  • Please click here to view and download the bid.
  • Please click here to view and download the project drawings.