Cupertino Union School District · Measure Z Update · October 2026

The first summer of Measure Z is built.

Over Summer 2026, eleven projects reached students: new TK/K playgrounds, cooler blacktops, and a new roof at Hyde. Here is what that work cost, how the district protects every bond dollar, and how the next six years of campus modernization will unfold.

11
projects completed across playgrounds, paving and roofing
$2,124,183
estimated below original budgets, combined
190
bond list items, now organized into 26 campus packages
2032
projected year the final campus modernizations finish

Costs are preliminary and will be finalized at closeout. Schedule reflects the program as of October 8, 2026.

Summer 2026 Projects

Playgrounds, paving and roofing, delivered

Each project below shows its original budget beside its estimated actual cost. The gold bar is the estimate; the grey bar is what the Board originally set aside.

Playgrounds

PRELIMINARY COSTS6 sites · $1.80M budgeted · $1.73M estimated

Roofing

PRELIMINARY COSTS1 site · $264,205 below budget
Aerial view of Hyde Middle School rooftops
COMPLETED SUMMER 2026

Hyde

Composition shingles were replaced, giving these buildings a new 25-year warranty. Hyde's remaining roofing work will be packaged with its future modernization so the campus is disrupted once, not twice.

Paving

PRELIMINARY COSTS4 sites · $3.73M budgeted · $1.94M estimated

Because of Board feedback, all four paving projects include solar reflective pavement coating, which helps cool play surfaces and reduce urban heat island effects. At Lincoln, the coating was not in the original budget, which is why its estimate runs above the original figure.

Summer 2026 at a glance

Original budgets compared with estimated actual costs, drawn to the same scale. Final figures will be confirmed at closeout.

Original budgetEstimated actual
Budgeted $6,227,703Estimated $4,103,520Difference $2,124,183
Program Contingency

Savings stay in the program, and the Board holds the key

Measure Z keeps a single district-wide contingency. When a project finishes under budget, the savings return to it. When a project needs more, staff must ask, and the Board decides.

Project finishesunder budget spent savings DISTRICT-WIDE CONTINGENCY BOARD Project needs more funds overage
  1. A project needs additional fundsA gap is confirmed through design or site work.
  2. Staff brings a requestThe need, the cause and the amount go to the Board in public.
  3. The Board decidesTrustees weigh the request against the program as a whole.
  4. Funds are allocatedOnly an approved amount leaves the contingency.

Every use of contingency comes to the Board for approval.

Budgets sharpen as projects are defined

Today's budgets for future projects are planning-level. As design teams are hired and sites are investigated, the range of likely costs narrows, and some projects may reveal needs beyond their budget.

  1. Work within the current budget whenever possibleThe first priority is to deliver the scope within what was approved.
  2. Identify budget needs earlyOnce a gap is confirmed, and before the project proceeds.
  3. Request Board approvalWhen defined scope exceeds the allocation, the Board is asked to approve an increase.

The intent: the Board makes informed decisions.

Project Consolidation

One campus, one design team, one contractor

Rather than tackling a school's roofing one year and its HVAC the next, campus modernizations will be delivered as consolidated packages. The first begin at Stocklmeir, Eisenhower and Garden Gate over Summer 2027.

190bond list items

Each dot is one bond list item. Grouping is illustrative; package sizes vary by campus.

Current bond project list

Example elementary school: 8 separate projects

Electrical Upgrades
Fire Alarm Upgrade
Roofing
HVAC Replacement
Kitchen HVAC
Landscaping
Exterior Painting
Portable Modernization

Separate designs, separate bids, spread across multiple years.

Campus-wide modernization

Example elementary school: 1 consolidated project

Electrical Upgrades
Fire Alarm Upgrade
Roofing
HVAC Replacement
Kitchen HVAC
Landscaping
Exterior Painting
Portable Modernization

One design team and one general contractor overseeing all trades, finished in one or two summers.

Every project approved by the Board is still delivered.Consolidation changes how the work is packaged, not what gets built.

Program Schedule · As of October 8, 2026

Where Measure Z stands today

Work through 2027 is planned. Dates beyond 2027 are projections that will shift as each project is scoped. Diamonds mark expected substantial completion.

Planned Projected, subject to change Substantial completion Series A spend-down, May 2028
What comes next

The next milestones are already on the calendar.

With the first summer complete, attention turns to Summer 2027, when the first consolidated campus modernizations, district-wide fire alarm and re-roofing work, and new hardscape reach completion.

Source: Measure Z Project Update and Schedule, Cupertino Union School District with TBK Construction Management. Summer 2026 costs are preliminary and will be finalized at closeout.