Playgrounds, paving and roofing, delivered
Each project below shows its original budget beside its estimated actual cost. The gold bar is the estimate; the grey bar is what the Board originally set aside.
Playgrounds
PRELIMINARY COSTS6 sites · $1.80M budgeted · $1.73M estimatedRoofing
PRELIMINARY COSTS1 site · $264,205 below budgetHyde
Composition shingles were replaced, giving these buildings a new 25-year warranty. Hyde's remaining roofing work will be packaged with its future modernization so the campus is disrupted once, not twice.
Paving
PRELIMINARY COSTS4 sites · $3.73M budgeted · $1.94M estimatedBecause of Board feedback, all four paving projects include solar reflective pavement coating, which helps cool play surfaces and reduce urban heat island effects. At Lincoln, the coating was not in the original budget, which is why its estimate runs above the original figure.
Summer 2026 at a glance
Original budgets compared with estimated actual costs, drawn to the same scale. Final figures will be confirmed at closeout.
Savings stay in the program, and the Board holds the key
Measure Z keeps a single district-wide contingency. When a project finishes under budget, the savings return to it. When a project needs more, staff must ask, and the Board decides.
- A project needs additional fundsA gap is confirmed through design or site work.
- Staff brings a requestThe need, the cause and the amount go to the Board in public.
- The Board decidesTrustees weigh the request against the program as a whole.
- Funds are allocatedOnly an approved amount leaves the contingency.
Every use of contingency comes to the Board for approval.
Budgets sharpen as projects are defined
Today's budgets for future projects are planning-level. As design teams are hired and sites are investigated, the range of likely costs narrows, and some projects may reveal needs beyond their budget.
- Work within the current budget whenever possibleThe first priority is to deliver the scope within what was approved.
- Identify budget needs earlyOnce a gap is confirmed, and before the project proceeds.
- Request Board approvalWhen defined scope exceeds the allocation, the Board is asked to approve an increase.
The intent: the Board makes informed decisions.
One campus, one design team, one contractor
Rather than tackling a school's roofing one year and its HVAC the next, campus modernizations will be delivered as consolidated packages. The first begin at Stocklmeir, Eisenhower and Garden Gate over Summer 2027.
Each dot is one bond list item. Grouping is illustrative; package sizes vary by campus.
Example elementary school: 8 separate projects
Separate designs, separate bids, spread across multiple years.
Example elementary school: 1 consolidated project
One design team and one general contractor overseeing all trades, finished in one or two summers.
Every project approved by the Board is still delivered.Consolidation changes how the work is packaged, not what gets built.
Where Measure Z stands today
Work through 2027 is planned. Dates beyond 2027 are projections that will shift as each project is scoped. Diamonds mark expected substantial completion.
The next milestones are already on the calendar.
With the first summer complete, attention turns to Summer 2027, when the first consolidated campus modernizations, district-wide fire alarm and re-roofing work, and new hardscape reach completion.
Source: Measure Z Project Update and Schedule, Cupertino Union School District with TBK Construction Management. Summer 2026 costs are preliminary and will be finalized at closeout.